Permits & Reviews
Track permit applications and reviewer feedback
PRM-2024-0891
Site Plan Review
David Park
Senior Planner • 2 hours ago
Please clarify the stormwater management plan in section 4.2. We need additional details on the detention basin sizing calculations.
Lisa Thompson
Drainage Engineer • 1 hour ago
Agree with David. Also, the grading plan shows a 1.5% slope near the north perimeter—verify this meets our minimum standards.
PRM-2024-0887
Building Permit
Michael Chen
Building Official • 3 days ago
Resubmittal required. Fire-rated wall assembly details in Appendix B do not meet IBC 706 requirements. Please reference approved assemblies.
Patricia Garcia
Fire Safety Inspector • 2 days ago
Additionally, egress calculations need review. With the proposed unit count, verify sufficient stairwell width per IBC Table 1005.2.2.
Michael Chen
Building Official • 1 day ago
Resubmit with corrected details and we can move forward. Target review window is 5 business days after receipt.
PRM-2024-0879
Zoning Variance
Rebecca Wilson
Zoning Administrator • 5 days ago
Variance approved. Setback reduction from 25ft to 20ft granted based on lot configuration constraints. Condition: landscaping buffer as specified in plan set.
PRM-2024-0872
Stormwater Review
James Morrison
Stormwater Manager • 1 week ago
Stormwater plan approved. Bioretention areas and underground detention meet post-construction standards. Final inspection required before certificate of occupancy.
PRM-2024-0893
Demolition Permit
Angela Price
Demolition Inspector • 4 hours ago
Need asbestos survey report before permit approval. Please provide NESHAP documentation.
PRM-2024-0895
Special Use Permit
System
Admin • 2 days ago
Application received. Scheduled for review committee meeting on March 25.